Document | Document Requirements | Upload Requirements | Examples |
---|
Hired Plant Inspection Report - Concrete Booms & Pumps Anchor |
---|
| concreteboomsandpumps |
---|
| concreteboomsandpumps |
---|
|
Download the Inspection Report Template
| - Correct form used - LLE902G Concrete Booms & Pumps Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on page 3 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report – Cranes incl. Crane Trucks
Download the Inspection Report Template
| - Correct form used - LLE902H Cranes (incl. Crane Trucks) Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on pages 3-4 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report – Earthmoving Plant Anchor |
---|
| earthmovingplant |
---|
| earthmovingplant |
---|
|
Download the Inspection Report Template
| - Correct form used - LLE902I Earthmoving Plant Hired Plant Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on pages 3-4 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
| - Correct form used - LLE902J EWP Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on page 3 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report – Heavy Vehicle
Download the Inspection Report Template
| - Correct form used - LLE902K Heavy Vehicle Hired Plant Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on page 3 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report – Paving Plant
Download the Inspection Report Template
| - Correct form used - LLE902M Paving Plant Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on page 3 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report – Piling and Drilling Rigs Anchor |
---|
| pilinganddrillrigs |
---|
| pilinganddrillrigs |
---|
|
Download the Inspection Report Template
| - Correct form used - LLE902N Piling & Drilling Rigs Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on page 3 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report – Rail Plant
Download the Inspection Report Template
| - Correct form used - LLE902R Rail Plant Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
- All owner checks pages 2-3 ticked ok. If not comments section completed
- All three signature boxes on pages 3-4 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report - Light Vehicles Anchor |
---|
| lightvehicles |
---|
| lightvehicles |
---|
|
Download the Inspection Report Template
| - Correct form used - LLE906E Light Vehicle Hired Plant Inspection Report
- All sections of plant details box top of page 1 complete
- All minimum light vehicle requirements boxes page 1 ticked and cross ticked by LLE
- All owner checks pages 1-2 ticked ok. If not comments section completed
- Signature boxes on page 2 completed, signed and dated by owner and LLE
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |
Hired Plant Inspection Report – Small Plant
Download the Inspection Report Template
| - Correct form used - LLE902P Small Plant (Including Towable Plant) Hired Plant Inspection Report
- All sections of plant details box top of page 1 complete
- All mandatory requirements boxes page 1 ticked and cross ticked by LLE
- All owner checks pages 1-3 ticked ok. If not comments section completed
- All three signature boxes on page 3 completed, signed and dated
- Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Lendlease Project Personnel'
| Issue Date = As per report Expiry Date = 5 years from date of issue | |