titleAppointment and Nomination Forms

Anchor
whcappointmentforms
whcappointmentforms

CertificationCertification RequirementsUpload RequirementsExamples

Whitehaven Coal Contract Owner Appointment Form


This business rule was last updated by WHC on 15.01.2018

  • Document must be fully completed and signed by all required WHC personnel in all signature blocks
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Name of appointee – Contract Owner as listed on FORM 1
  •  Sites must be listed
  • WHC Contract Coordinator - must complete name, signature and date. Name must match FORM 1.
  • Appointed by – signed as per FORM 1
  • Black and white or colour copy is accepted
  • The mine operator or relevant manager must sign the form
  • Whitehaven Coal Contract Owner Appointment Form to be completed and uploaded in Portal and Onsite.
  • Contract Owner is not needed for class A
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1 - valid for 3 years

Whitehaven Coal Contract Coordinator Appointment Form


This business rule was last updated by WHC on 28.03.2018

  • Document must be fully completed and signed by all required WHC personnel in all signature blocks
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Name of appointee – Contract Coordinator as listed FORM 2 and FORM 1
  • Sites must be listed
  • WHC Contract Coordinator - must complete name, signature and date. Name must match FORM 1.
  • Appointed by – must match FORM 1
  • The mine operator or relevant manager must sign the form
  • Whitehaven Coal Contract Coordinator Appointment Form to be completed and uploaded in Portal and Onsite.
  • Black and white or colour copy is accepted
  • If form 1 is stating several contract coordinators, all forms for contract coordinators should be uploaded in the portal
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1 - valid for 3 years

Contractor Company Supervisor Nomination Form


This business rule was last updated by WHC on 15.01.2018

  • Document must be fully completed and signed in all signature blocks
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Contract company supervisor – must match FORM 1
  • Site/Area; WHC Contract Owner (Class B & C); WHC Coordinator – must be completed as per site required
  • Approval (Site or Area) must complete name, signature and date. Name must match FORM 1.
  • The mine operator or relevant manager must sign the form
  • Whitehaven Coal Company Supervisor form to be completed and uploaded in Portal and Onsite.
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date   of document signature by contracting company
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1 - valid for 3 years

Whitehaven Coal Authority to Undertake Induction
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Authority to Undertake Induction form to be completed and uploaded
  • Black and white or colour copy is accepted

NOTE: All people intending to work underground need Gerald Linde or Brian Williams to sign off on the ATUI (form 3) and Form 2

  • MEM - all mechanical trades (Surface and UG) (Richard Hokin)
  • EEM  - all electrical trades (Surface and UG) (Chris Bentham)
  • CHPP, Surface  Civil and Engineering - (Aron Cane)
  • Surface Drilling, Enviro, cultural Heritage and Tech Services - (Owen Salisbury or Dave Ellwood )
  • Safety and Training - (Scott Ginnivan)

Example:

If U/G mechanical trade then Gerald or Brian AND Richard Hokin to sign.

If enviro work then only Owen or Dave to sign

  •  Issue date to be recorded as the date of document approval by WHC
 
Expand
titleContractor Details
CertificationCertification RequirementsUpload RequirementsExamples

Head Contractor Details

  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Head contractor Company details to be displayed
  • Black and white or colour copy is accepted
  • Issue date to be recorded as the date of submission
  • Expiry date to be calculated as 6 months from Issue date
 

Anchor
subcontractorform
subcontractorform
Subcontractor Details

  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Subcontractor Company details to be displayed
  • Black and white or colour copy is accepted
  • Issue date to be recorded as the date of submission
  • Expiry date to be calculated as 6 months from Issue date
 
Expand
titleContractor Engagement
CertificationCertification RequirementsUpload RequirementsExamples

Anchor
contractorengagementform1
contractorengagementform1
Whitehaven Coal Contractor Engagement Form 1


This business rule was last updated by WHC on 15.01.2018


  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Contractor company supervisor box must be completed
  • Site/Area – must be listed as per site required; WHC Contractor Owner (class B & C) – must be listed; WHC Contract Coordinator(s) – must be listed – One contract coordinator per site, the contract owner might or might not be the same for all sites listed
  • Scope of Work section must be listed
  • Contractor Classification must be ticked and must match class in Onsite.
  • Duration of work, cost, & people must be completed
  • Contractor management section all questions completed
  • Notifications to relevant WHC department - optional
  • Approval – must have name printed, must be signed and dated. Must be completed in accordance to the site listed in the field – Site/Area on this form. 
    List of authorised approvers can be found HERE
  • Whitehaven Coal Contractor Engagement Form 1 to be completed and uploaded
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration to be recorded 3 years from starting date except if stated otherwise in the document.

WHC-FRM-SUB-CONTRACTOR ENGAGEMENT –Form 5


This business rule was last updated by WHC on 15.01.2018


  • Primary Contracting company details must be displayed on form
  • Sub- Contracting company details must be displayed on form.
  • Primary Contracting company details must match registered company details in Onsite
  • Primary contactor company -  must be listed with contact details and company to match FORM 1.
  • Sub- contractor company - must be listed with contact details
  • Site/Area; WHC Contract Owner (Class B & C); WHC Coordinator(s)
  • Scope of work completed
  • Approval – Must have name printed, signature and dated. Contract owner must match form 2.  
  • Duration of work, cost, & people must be completed
  • Sub-contractor management – all fields completed
  • Approval (site or area) – WHC contract owner must match FROM 2. Must have name, signature and date.
  • Acknowledgement – Primary contractor company supervisor name must match FORM 1.
  • Form 5 must be fully completed before upload
  • Black and white or colour copy is accepted

NOTE: Sub-contractors of sub-contractors will be related to the primary contractor.

NOTE: *When form 5 is uploaded for a sub-contractor and the primary contractor has registered as an uncategorized contractor - send form 5 to site for approval*

  • Form(s) can be uploaded separately or as a bundle.
  • 1 form per sub-contractor
  • Expiration date as per Whitehaven Coal ContractorEngagement Form 1 – valid for 3 years
Expand
titleHSE Documentation

Anchor
hsedocumentation
hsedocumentation

CertificationCertification RequirementsUpload RequirementsExamples

Whitehaven Coal HSE Document Form 2


This business rule was last updated by WHC on 1524.0204.2018


Business Rule for Form
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Contractor Company Supervisor – listed
  • Site/Area; WHC Contract Owner (class B & C); WHC contract Coordinator – must match details listed on FORM 1
  • WHC Group Standards – OC and/or Narrabri mine section completed. 
  • Other relevant WHC standards or procedures – optional
  • WHC (OC) and/or WHC (NCO) Approvals – must match FORM 1. Must have name printed, signed and dated. 1 Mine operator minimum or relevant manager must sign for his area for OC, U/G need 3 signatures for MME, electrical and mechanical Engineering
    List of authorised approvers can be found HERE
  • Contractor Company Acknowledgement must be completed – the Class must match FORM 1, name needs to be inserted in statement.
  • The class must be selected, to confirm that they agree to classification given
  • Contractor company supervisor – Must have name printed, signature and dated.
  • Approval – Must have name printed, signature and dated.
  • Whitehaven Coal H&C Document Form 2 to be completed and uploaded
  • Black and white or colour copy is accepted

 

NOTE: All people intending to work underground need Gerald Linde or Brian Williams to sign off on the ATUI (form 3) and Form 2

  • MEM - all mechanical trades (Surface and UG) (Richard Hokin)
  • EEM  - all electrical trades (Surface and UG) (Chris Bentham)
  • CHPP, Surface  Civil and Engineering - (Aron Cane)
  • Surface Drilling, Enviro, cultural Heritage and Tech Services - (Owen Salisbury or Dave Ellwood )
  • Safety and Training - (Scott Ginnivan)

Example:

If U/G mechanical trade then Gerald or Brian AND Richard Hokin to sign.

If enviro work then only Owen or Dave to sign

 

 

  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1 – valid for 3 years