Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Expand
titleAppointment and Nomination Forms

Anchor
whcappointmentforms
whcappointmentforms

CertificationCertification RequirementsUpload RequirementsExamples

Whitehaven Coal Contract Owner Appointment Form

  • Document must be fully completed and signed by all required WHC personnel in all signature blocks
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1

 

Whitehaven Coal Contract Coordinator Appointment Form

  • Document must be fully completed and signed by all required WHC personnel in all signature blocks
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1

 

Contractor Company Supervisor Nomination Form

  • Document must be fully completed and signed in all signature blocks
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document signature by contracting company
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1

 

Whitehaven Coal Authority to Undertake Induction
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Authority to undertake Induction form to be completed and uploaded
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document approval by WHC
Image Added
Expand
titleContractor Details
CertificationCertification RequirementsUpload RequirementsExamples

Head Contractor Details

  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Head contractor Company details to be displayed
  • Black and white or colour copy is accepted
  • Issue date to be recorded as the date of submission
  • Expiry date to be calculated as 6 months from Issue date
 

Anchor
subcontractorform
subcontractorform
Subcontractor Details

  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Subcontractor Company details to be displayed
  • Black and white or colour copy is accepted
  • Issue date to be recorded as the date of submission
  • Expiry date to be calculated as 6 months from Issue date
 
Expand
titleContractor Engagement
CertificationCertification RequirementsUpload RequirementsExamples
Anchor
contractorengagementform1
contractorengagementform1
Whitehaven Coal Contractor Engagement Form 1
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration to be recorded as Issue date plus duration of project (can be found in the responses to the questionnaire)
Anchor
SubContractorEngagementForm5
SubContractorEngagementForm5

Whitehaven Coal Sub-contractor Engagement Form 5 (Subcontractor engaged by a primary contractor)

  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Black and white or colour copy is accepted
  • Document must be fully completed and signed in all signature blocks by Contract owner, Contract coordinator and nominated contractor company supervisor. Names of people required to sign can be identified in the appropriate forms that must also be uploaded (see below)
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1

Whitehaven Coal Sub-contractor Engagement Form 5 (Uploaded by primary contractor for subcontractors they engage)

  • Forms are uploaded but not against a cert – need to be transferred to non-verified cert
  • Document must be fully completed and signed in all signature blocks by Contract owner, Contract coordinator and nominated contractor company supervisor. Names of people required to sign can be identified in the appropriate forms that must also be uploaded (see below)
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1
 
Expand
titleHSC DocumentDocumentation

Anchor
hscdocumenthandcdocform2hscdocument
handcdocform2

CertificationCertification RequirementsUpload RequirementsExamples
Whitehaven Coal HSC Document Form 2
  • Document must be fully completed and signed by all required WHC personnel
  • If company has selected Narrabri as the site they are working at then all three signature bloclks must be signed. Contract owner / coordinator names can be identified in the appropriate forms that must also be uploaded (see below)
  • If the company has selected only Open Cut site(s) then only the Open Cut signature block needs to be completed.
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Black and white or colour copy is accepted
  • Issue date to be recorded as Date of document approval by WHC
  • Expiration date as per Whitehaven Coal Contractor Engagement Form 1
 

 

 
Expand
titleHSE Documentation

Anchor
hsedocumentation
hsedocumentation

CertificationCertification RequirementsUpload RequirementsExamples

Head Contractor Details

  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Head contractor Company details to be displayed
  • Black and white or colour copy is accepted
  • Issue date to be recorded as the date of submission
  • Expiry date to be calculated as 6 months from Issue date
  AnchorsubcontractorformsubcontractorformSubcontractor Details
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Subcontractor Company details to be displayed
  • Black and white or colour copy is accepted
  • Issue date to be recorded as the date of submission
  • Expiry date to be calculated as 6 months from Issue date
  Anchorhandcdocform2handcdocform2Whitehaven Coal H&C Document Form 2Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Whitehaven Coal H&C Document Form 2 to be completed and uploaded
  • Black and white or colour copy is accepted
    • Issue date to be recorded as Date of document approval by WHC
    • Expiration date as per Whitehaven Coal Contractor Engagement Form 1
     

    Anchor
    ClassBContractorHSEPlan
    ClassBContractorHSEPlan
    Whitehaven Coal Class B Contractor HSE Plan

    • Contracting company details must be displayed on form
    • Contracting company details must match registered company details in Onsite
    • Whitehaven Coal Class B Contractor HSE Plan to be completed and uploaded
    • Black and white or colour copy is accepted
    • Issue date to be recorded as Date of document approval by WHC
    • Expiration date as per Whitehaven Coal Contractor Engagement Form 1
    Image Modified

    System.Contractor Management.WHC-FRM-Contractor HSE Documents Form 2

    • Contracting company details must be displayed on form
    • Contracting company details must match registered company details in Onsite
    • HSE Documents Form 2
    to be completed and uploaded
  • Black and white or colour copy is accepted
    • Issue date to be recorded as Date of document approval by WHC
    Image RemovedWhitehaven Coal Authority to Undertake Induction
  • Contracting company details must be displayed on form
  • Contracting company details must match registered company details in Onsite
  • Authority to undertake Induction form
    • to be completed and uploaded
    • Black and white or colour copy is accepted
    • Issue date to be recorded as Date of document approval by WHC
    Image Modified