Safety.Induction.Open Cut and Generic ATUI Form | Click HERE to access a copy of the form
The form should be fully completed to be accepted All All 6 pages of the form must be included within the uploaded fileThe role of the person is listed i.e. Operator / Coal loader.The primary location must be listed.The 'induction required' would ideally be listed on the form however if this has been missed in completing the form it can still be acceptedFor sign offuploaded Page 1 - Name of inductee must match registering person
- Position must be completed
- Contractor Company must be completed
- WHC Contract Owner or Coordinator email – NOT MANDATORY
- Must select Primary WHC site and all sections must be completed.
- Induction(s) required – must be completed
- Approval section:
The contract owner or
Contract always - needs to be listed, they must sign and date.
The mechanical or electrical is only required if the role is linked to any mechanical or electrical role
. The Manager of Mining engineering needs to sign for ALL underground trades and Operator for Narrabri - NOTE: MME sign off not needed for surface role at Narrabri
- The Manager of Mining engineering (MME) needs to sign
onto the form anyone that selected titled - 'All Open Cut - Operator'.
NOTE: Gunnedah CHPP does not have a MME – therefore this signature is not required for applicants that have indicated Gunnedah CHPP is as their primary WHC site even if the 'All Open Cut - Operator' role has been chosen. Page 2 - Inductions; Check list must be completed
Page 3 - Roles; A role in the Open Cut section must be selected
Page 4, 5 & 6 Only version 8 ,9 and 10 & 11 will be accepted. Note: The Whitehaven Coal Induction Information Form issued by Pegasus is not an acceptable form for this competency upload Version 10 accepted until 31st March 2019 | |
|