Hired Plant Inspection Report - Concrete Booms & Pumps

Anchor
concreteboomsandpumps
concreteboomsandpumps

 
: LLE902G Concrete Booms & Pumps


  • Correct form used - LLE902G Concrete Booms & Pumps Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on page 3 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =

1 year

5 years from date of issue

Hired Plant Inspection Report – Cranes incl. Crane Trucks

Anchor
cranes
cranes

Download the Inspection Report Template

: LLE902H Cranes (incl. Crane Trucks)


  • Correct form used - LLE902H Cranes (incl. Crane Trucks) Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on pages 3-4 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report – Earthmoving Plant

Anchor
earthmovingplant
earthmovingplant

Download the Inspection Report Template

: LLE902I Earthmoving Plant Hired Plant

 


  • Correct form used - LLE902I Earthmoving Plant Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on pages 3-4 completed, signed and dated
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report -  EWP

Anchor
ewp
ewp

Download the Inspection Report Template

: LLE902J EWP


  • Correct form used - LLE902J EWP Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on page 3 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report – Heavy Vehicle

Anchor
heavyvehicle
heavyvehicle

Download the Inspection Report Template

LLE902K Heavy Vehicle Hired Plan 


  • Correct form used - LLE902K Heavy Vehicle Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on page 3 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report – Paving Plant

Anchor
pavingplant
pavingplant

Download the Inspection Report Template

: LLE902M Paving Plant


  • Correct form used - LLE902M Paving Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on page 3 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 


Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report – Piling and Drilling Rigs

Anchor
pilinganddrillrigs
pilinganddrillrigs

Download the Inspection Report Template

LLE902N Piling & Drilling Rigs 


  • Correct form used - LLE902N Piling & Drilling Rigs Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on page 3 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report – Rail Plant

Anchor
railplant
railplant

Download the Inspection Report Template

: LLE902R Rail Plant

 


  • Correct form used - LLE902R Rail Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
All three signature boxes on pages 3-4 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report - Light Vehicles

Anchor
lightvehicles
lightvehicles

Download the Inspection Report Template

: LLE906E Light Vehicle Hired Plant


  • Correct form used - LLE906E Light Vehicle Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All minimum light vehicle requirements boxes page 1 ticked and cross ticked by LLE
  • All owner checks pages 1-2 ticked ok. If not comments section completed
  • Signature boxes on page 2 completed, signed and dated by owner and LLE
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year from
5 years from date of issue

Hired Plant Inspection Report – Small Plant

Anchor
smallplant
smallplant

Download the Inspection Report Template

: LLE902P Small Plant (Including Towable Plant) Hired Plant

 


  • Correct form used - LLE902P Small Plant (Including Towable Plant) Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes page 1 ticked and cross ticked by LLE
  • All owner checks pages 1-3 ticked ok. If not comments section completed
All three signature boxes on page 3 completed, signed and dated
  • Parts of the form that are required to be signed and dated 
    • Owners inspectors 
    • Owners representative
    • Acciona authorised approver
  • Click HERE to view a list of authorised approvers which can sign off on the section which states 'To Be Completed By Acciona Project Personnel'

Please note in the bottom table of the form not all signatures are required as long they have been signed off throughout the document 

Issue Date = As per report
Expiry Date =
1 year
5 years from date of issue