Competency Name | Competency Requirements | Upload Requirements | Examples |
---|
Site.Trained.SMIC Training - Demolition - Introduction | When statement of attainment is uploaded: - RTO Name, National Provider Code / RTO Number & Logo to be displayed on document - Pegasus Administrators to click here for instructions on verifying RTOs
- Name on certificate to match the name in the system (shortened versions accepted e.g.. 'Chris' accepted for Christopher)
- Completion date or issue date must be displayed
- Name and / or signature of issuer
- Document / Certificate / Statement of Attainment Number
- Nationally Recognised Training logo
- No expiry
- Must show completion of the following units of competency:
- CPCCOHS2001A - Apply OHS requirements, policies and procedures in the construction industry
- CPCCDE3016A - Identify hazards on demolition sites and apply risk management strategies
- CPCCDE3020A - Select and use tools and equipment for hot work in the demolition industry
- CPCCDE3017A - Select and use hand tools and equipment for demolition tasks
When transcript (accepted in lieu of SOA) is uploaded: - RTO Name & Logo to be displayed on document - Pegasus Administrators to click here for instructions on verifying RTOs
- Name on transcript / statement of results / academic history report to match the name in the system (shortened versions accepted e.g. 'Chris' accepted for Christopher)
- Completion date or issue date must be displayed
- If individual unit results are displayed the result needs to indicate completion / pass result. Grading categories can be referenced HERE
- No expiry
- Must show completion of the following units of competency:
- CPCCOHS2001A - Apply OHS requirements, policies and procedures in the construction industry
- CPCCDE3016A - Identify hazards on demolition sites and apply risk management strategies
- CPCCDE3020A - Select and use tools and equipment for hot work in the demolition industry
- CPCCDE3017A - Select and use hand tools and equipment for demolition tasks
Note: Temporary letter or receipt confirming card or replacement card has been ordered (letter written by issuing authority / RTO) may be accepted for this competency upload but only for a time frame of 60 days as nominated on the document. Following this expiry, it is expected the card / certificate will now be uploaded. | When statement of attainment is uploaded:
- Issue Date =
- Completion date - if listed on certificate (this completion date is always used when displayed)
- Issue date - If only an issue date is listed please enter this as the issue date
- Expiry Date = None
When transcript (accepted in lieu of SOA) is uploaded: - Issue Date =
- Completion date - if listed on certificate (this completion date is always used when displayed)
- Issue date - If only an issue date is listed please enter this as the issue date
- If there is a 'from' and a 'to' completion date shown indicating the course was complete over a time frame longer than 1 day, use the 'to' date as the issue date within
- Expiry Date = None
|
|
Site.Trained.SMIC Training - Demolition - Experienced | When statement of attainment is uploaded: - RTO Name, National Provider Code / RTO Number & Logo to be displayed on document - Pegasus Administrators to click here for instructions on verifying RTOs
- Name on certificate to match the name in the system (shortened versions accepted e.g.. 'Chris' accepted for Christopher)
- Completion date or issue date must be displayed
- Name and / or signature of issuer
- Document / Certificate / Statement of Attainment Number
- Nationally Recognised Training logo
- No expiry
- Must show completion of the following units of competency:
- CPCCCM2001A - Read and interpret plans and specifications
- CPCCDE3016A - Identify hazards on demolition sites and apply risk management strategies
- CPCCDE3019A - Demolish small buildings and structures using hand tools and small plant and equipment
- CPCCDE3018A - Select and use small plant and equipment for demolition tasks
- CPCCDE3020A - Select and use tools and equipment for hot work in the demolition industry
- CPCCDE3017A - Select and use hand tools and equipment for demolition tasks
When transcript (accepted in lieu of SOA) is uploaded: - RTO Name & Logo to be displayed on document - Pegasus Administrators to click here for instructions on verifying RTOs
- Name on transcript / statement of results / academic history report to match the name in the system (shortened versions accepted e.g. 'Chris' accepted for Christopher)
- Completion date or issue date must be displayed
- If individual unit results are displayed the result needs to indicate completion / pass result. Grading categories can be referenced HERE
- No expiry
- Must show completion of the following units of competency:
- CPCCCM2001A - Read and interpret plans and specifications
- CPCCDE3016A - Identify hazards on demolition sites and apply risk management strategies
- CPCCDE3019A - Demolish small buildings and structures using hand tools and small plant and equipment
- CPCCDE3018A - Select and use small plant and equipment for demolition tasks
- CPCCDE3020A - Select and use tools and equipment for hot work in the demolition industry
- CPCCDE3017A - Select and use hand tools and equipment for demolition tasks
Note: Temporary letter or receipt confirming card or replacement card has been ordered (letter written by issuing authority / RTO) may be accepted for this competency upload but only for a time frame of 60 days as nominated on the document. Following this expiry, it is expected the card / certificate will now be uploaded. | When statement of attainment is uploaded:
- Issue Date =
- Completion date - if listed on certificate (this completion date is always used when displayed)
- Issue date - If only an issue date is listed please enter this as the issue date
- Expiry Date = None
When transcript (accepted in lieu of SOA) is uploaded: - Issue Date =
- Completion date - if listed on certificate (this completion date is always used when displayed)
- Issue date - If only an issue date is listed please enter this as the issue date
- If there is a 'from' and a 'to' completion date shown indicating the course was complete over a time frame longer than 1 day, use the 'to' date as the issue date within
- Expiry Date = None
|
|
Site.Trained.SMIC Training - Demolition - Nominated Supervisor | When statement of attainment is uploaded: - RTO Name, National Provider Code / RTO Number & Logo to be displayed on document - Pegasus Administrators to click here for instructions on verifying RTOs
- Name on certificate to match the name in the system (shortened versions accepted e.g.. 'Chris' accepted for Christopher)
- Completion date or issue date must be displayed
- Name and / or signature of issuer
- Document / Certificate / Statement of Attainment Number
- Nationally Recognised Training logo
- No expiry
- Must show completion of the following units of competency:
- CPCCOHS2001A - Apply OHS requirements, policies and procedures in the construction industry
- CPCCBC4002A - Manage occupational health and safety in the building and construction workplace
- CPCCDE3016A - Identify hazards on demolition sites and apply risk management strategies
- CPCCDE3018A - Select and use small plant and equipment for demolition tasks
- CPCCDE3020A - Select and use tools and equipment for hot work in the demolition industry
- CPCCDE3019A - Demolish small buildings and structures using hand tools and small plant and equipment
- CPCCDE3022A - Manage demolition recyclable and waste materials using load shifting equipment
- CPCCBC4012B - Read and interpret plans and specifications
- CPCCDE4001A - Plan and prepare for activities on demolition sites
- CPCCDE4002A - Plan and supervise demolition work to minimise environmental and public health and safety impact
- CPCCDE4003A - Supervise individual activities on demolition sites
- CPCCDE4004A - Finalise demolition activities and supervise property handover
When transcript (accepted in lieu of SOA) is uploaded: - RTO Name & Logo to be displayed on document - Pegasus Administrators to click here for instructions on verifying RTOs
- Name on transcript / statement of results / academic history report to match the name in the system (shortened versions accepted e.g. 'Chris' accepted for Christopher)
- Completion date or issue date must be displayed
- If individual unit results are displayed the result needs to indicate completion / pass result. Grading categories can be referenced HERE
- No expiry
- Must show completion of the following units of competency:
- CPCCOHS2001A - Apply OHS requirements, policies and procedures in the construction industry
- CPCCBC4002A - Manage occupational health and safety in the building and construction workplace
- CPCCDE3016A - Identify hazards on demolition sites and apply risk management strategies
- CPCCDE3018A - Select and use small plant and equipment for demolition tasks
- CPCCDE3020A - Select and use tools and equipment for hot work in the demolition industry
- CPCCDE3019A - Demolish small buildings and structures using hand tools and small plant and equipment
- CPCCDE3022A - Manage demolition recyclable and waste materials using load shifting equipment
- CPCCBC4012B - Read and interpret plans and specifications
- CPCCDE4001A - Plan and prepare for activities on demolition sites
- CPCCDE4002A - Plan and supervise demolition work to minimise environmental and public health and safety impact
- CPCCDE4003A - Supervise individual activities on demolition sites
- CPCCDE4004A - Finalise demolition activities and supervise property handover
Note: Temporary letter or receipt confirming card or replacement card has been ordered (letter written by issuing authority / RTO) may be accepted for this competency upload but only for a time frame of 60 days as nominated on the document. Following this expiry, it is expected the card / certificate will now be uploaded. | When statement of attainment is uploaded:
- Issue Date =
- Completion date - if listed on certificate (this completion date is always used when displayed)
- Issue date - If only an issue date is listed please enter this as the issue date
- Expiry Date = None
When transcript (accepted in lieu of SOA) is uploaded: - Issue Date =
- Completion date - if listed on certificate (this completion date is always used when displayed)
- Issue date - If only an issue date is listed please enter this as the issue date
- If there is a 'from' and a 'to' completion date shown indicating the course was complete over a time frame longer than 1 day, use the 'to' date as the issue date within
- Expiry Date = None
|
|
CPCCDE3016A Identify hazards on demolition sites and apply risk management strategies Onsite competency name TBC |
|
|
|
CPCCDE3018A Select and use small plant and equipment for demolition tasks Onsite competency name TBC |
|
|
|
CPCCDE3019A Demolish small buildings and structures using hand tools and small plant and equipment Onsite competency name TBC |
|
|
|
CPCCDE3020A Select and use tools and equipment for hot work in the demolition industry Onsite competency name TBC |
|
|
|
CPCCDE3022A Manage demolition recyclables and waste materials using loading shifting equipment Onsite competency name TBC |
|
|
|
CPCCDE4001A Plan and prepare for activities on demolition sites Onsite competency name TBC |
|
|
|
CPCCDE4002A Plan and supervise demolition works to minimise environmental and public health and safety impact Onsite competency name TBC |
|
|
|
CPCCDE4003A Supervise individual activities on demolition sites Onsite competency name TBC |
|
|
|
CPCCDE4004A Finalise demolition activities and supervise property handover Onsite competency name TBC |
|
|
|