- This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
If SOA is uploaded: - It must be issued by an RTO and it must show the relevant unit of competency, as well as:
- Identify the RTO by its national provider number
- Shows the Nationally Recognised Training (NRT) logo
- Only the issue date (shown as date of completion on document) needs to be recorded in Onsite
| |
Anchor |
---|
| doggerhighrisk |
---|
| doggerhighrisk |
---|
| Dogger.High Risk Licence.Perform Dogging (DG)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes DG, RB, RI or RA to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Image Added Temporary Letter of Assessment Document: Image Added Image Added |
Anchor |
---|
| riggerhighriskbasic |
---|
| riggerhighriskbasic |
---|
| Rigger.High Risk Licence.Licence to perform rigging basic (RB)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes RB, RI or RA to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
| - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Anchor |
---|
| riggerhighriskintermediate |
---|
| riggerhighriskintermediate |
---|
| Rigger.High Risk Licence.Licence to perform rigging intermed (RI)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes RI or RA to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Anchor |
---|
| riggerhighriskadvanced |
---|
| riggerhighriskadvanced |
---|
| Rigger.High Risk Licence.Licence to perform rigging advanced (RA)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code RA to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Elevated Work Platform.High Risk Licence.Boom-type elevating work platform (WP)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code WP to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added Image Added |
Anchor |
---|
| forklifthighrisk |
---|
| forklifthighrisk |
---|
| Operator Forklift.High Risk Licence.Licence to operate a forklift (LF)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code LF to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
|
High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
| - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes SB, SI or SA to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
| - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes SI or SA to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
| - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code SA to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane Bridge & Gantry.High Risk Licence.Operate Bridge and Gantry Cranes (CB)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code CB to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane Portal Boom.High Risk Licence.Licence to Operate a Portal Boom Crane (CP)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code CP to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane Tower.High Risk Licence.Licence to Operate Self Erecting Tower Crane (CS)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code CS to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane Tower.High Risk Licence.Tower cranes (CT)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code CT to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Forklift.Licence.High Risk - Operate Order Picking Forklift Truck (LO)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code LO to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- Only the front of this licence is required to be displayed in the file upload
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane.Conduct Telescopic Materials Handler Operations Licence | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code CN to be listed and matched also accepted are C6, C1 or C0 high risk work licence is required
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
|
|
Operator Crane.High Risk Licence.Operate a Non-slewing mobile crane >3T (CN)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code CN to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane.High Risk Licence.Operate a vehicle loading crane > 10T (CV)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes CV, C0, C1, C2 or C6 to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane.High Risk Licence.Slewing mobile cranes with a capacity over 100 tonnes (C0)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code C0 to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. |
- Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane.High Risk Licence.Slewing mobile cranes with a capacity up to 100 tonne (C1)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes C0, C1, C2 or C6 to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane.High Risk Licence.Slewing mobile cranes with a capacity up to 20 tonnes (C2)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes C0, C2 or C6 to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Operator Crane.High Risk Licence.Slewing mobile cranes with a capacity up to 60 tonnes (C6)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Either Class / Codes C0 or C6 to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Boom Concrete Placing.High Risk Licence.Concrete placing booms (PB)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code PB to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Crane Driver.High Risk Licence.Licence to Operate a Derrick Crane (CD)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code CD to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- .
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Hoist.High Risk Licence.Licence to Operate Material Hoist (HM)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code HM to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload.
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. | - Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.
| High Risk Licence: Image Added Temporary Notice of Assessment Document: Image Added Temporary Letter of Assessment Document: Image Added |
Hoist.High Risk Licence.Licence to Operate Personnel and Material Hoists (HP)
This Business rule was last updated by ARA on 01.04.2019 | - Name on Licence to match the person registered
- If licence has not yet been received by applicant, a temporary document titled 'Notice of Assessment' can be accepted for a period of 60 days from the completion date
A letter from the issuing organisation may also be accepted as a temporary document for one month from the issue date on the letter - Class / Code HP to be listed and matched to competency selection accordingly
- Black and white or colour acceptable
- Must be issued on Work safe or relevant Government Authority High Risk Licence
- Only the front of this licence is required to be displayed in the file upload
Please note: High risk licence renewal receipts can be accepted for a period of 4 weeks from the receipt date. |
- Issue and Expiry date to be recorded within Onsite as reflected on high risk licence.
- NOTE: Occasionally HRWL's will be uploaded with an issue date recorded that is a date in the future. This can be accepted by recording the expiry date only in Onsite with the knowledge that the 'forward date' on the HRWL is a result of continuation from a previous licences end date when renewal is complete
- HRWL renewal receipts= expiry date to be recorded 4 weeks from Issue/receipt date.