Hired Plant Inspection Report - Concrete Booms & Pumps

  • Correct form used - LLE902G Concrete Booms & Pumps Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated

Issue Date = As per report
Expiry Date = 1 year from date of issue

 
Hired Plant Inspection Report – Cranes incl. Crane Trucks
  • Correct form used - LLE902H Cranes (incl. Crane Trucks) Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on pages 3-4 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report – Earthmoving Plant
  • Correct form used - LLE902I Earthmoving Plant Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on pages 3-4 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report -  EWP
  • Correct form used - LLE902J EWP Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report – Heavy Vehicle
  • Correct form used - LLE902K Heavy Vehicle Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report – Paving Plant
  • Correct form used - LLE902M Paving Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report – Piling and Drilling Rigs
  • Correct form used - LLE902N Piling & Drilling Rigs Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report – Rail Plant
  • Correct form used - LLE902R Rail Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on pages 3-4 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report - Light Vehicles
  • Correct form used - LLE906E Light Vehicle Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All minimum light vehicle requirements boxes page 1 ticked and cross ticked by LLE
  • All owner checks pages 1-2 ticked ok. If not comments section completed
  • Signature boxes on page 2 completed, signed and dated by owner and LLE
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
Hired Plant Inspection Report – Small Plant
  • Correct form used - LLE902P Small Plant (Including Towable Plant) Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes page 1 ticked and cross ticked by LLE
  • All owner checks pages 1-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 
    
    