Competency | Competency Requirements | Upload Requirements | Examples |
---|
Site - Pre-Approval form / Authority to undertake induction form | - The form must be dated and must be signed by the WHC contract owner / coordinator
- Must be signed by relevant WHC manager if trade is being used
Example: Manager Mechanical Engineering or Manager Electrical Engineering - If going underground: Must be signed by manager mining engineering
| Saved in the general folder (not the competency tab) Whitehaven Open Cut: - Gets uploaded to the generic comp
Whitehaven Underground: - Admin. Letter of competency induction authorisation
| |
Access keys to be assigned: Check the Authority to Undertake Induction form. For each site selected they should have an access key. | |