DocumentDocument RequirementsUpload RequirementsExamples

Hired Plant Inspection Report - Concrete Booms & Pumps

 

Download the Inspection Report Template: LLE902G Concrete Booms & Pumps


  • Correct form used - LLE902G Concrete Booms & Pumps Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated

Issue Date = As per report
Expiry Date = 1 year from date of issue

 

Hired Plant Inspection Report – Cranes incl. Crane Trucks


Download the Inspection Report Template: LLE902H Cranes (incl. Crane Trucks)


  • Correct form used - LLE902H Cranes (incl. Crane Trucks) Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on pages 3-4 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report – Earthmoving Plant


Download the Inspection Report Template: LLE902I Earthmoving Plant Hired Plant

 

  • Correct form used - LLE902I Earthmoving Plant Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on pages 3-4 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report -  EWP


Download the Inspection Report Template: LLE902J EWP


  • Correct form used - LLE902J EWP Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report – Heavy Vehicle


Download the Inspection Report Template: LLE902K Heavy Vehicle Hired Plan

 

  • Correct form used - LLE902K Heavy Vehicle Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report – Paving Plant


Download the Inspection Report Template: LLE902M Paving Plant


  • Correct form used - LLE902M Paving Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report – Piling and Drilling Rigs


Download the Inspection Report Template: LLE902N Piling & Drilling Rigs

 

  • Correct form used - LLE902N Piling & Drilling Rigs Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report – Rail Plant


Download the Inspection Report Template: LLE902R Rail Plant

 

  • Correct form used - LLE902R Rail Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes pages 1-2 ticked and cross ticked by LLE
  • All owner checks pages 2-3 ticked ok. If not comments section completed
  • All three signature boxes on pages 3-4 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report - Light Vehicles


Download the Inspection Report Template: LLE906E Light Vehicle Hired Plant


  • Correct form used - LLE906E Light Vehicle Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All minimum light vehicle requirements boxes page 1 ticked and cross ticked by LLE
  • All owner checks pages 1-2 ticked ok. If not comments section completed
  • Signature boxes on page 2 completed, signed and dated by owner and LLE
Issue Date = As per report
Expiry Date = 1 year from date of issue
 

Hired Plant Inspection Report – Small Plant


Download the Inspection Report Template: LLE902P Small Plant (Including Towable Plant) Hired Plant

 

  • Correct form used - LLE902P Small Plant (Including Towable Plant) Hired Plant Inspection Report
  • All sections of plant details box top of page 1 complete
  • All mandatory requirements boxes page 1 ticked and cross ticked by LLE
  • All owner checks pages 1-3 ticked ok. If not comments section completed
  • All three signature boxes on page 3 completed, signed and dated
Issue Date = As per report
Expiry Date = 1 year from date of issue
 